Donnerstag, 17. Dezember 2015


On the 17th of December, 2015, Sulley, Stephen and I went to the site to change the motor control box because we realised it was not working fully authomatic. We realised that if the light goes off and later comes on, some one must open the power box to press the start bottom for the whole system to start, of which we don't want them to be opening the power bottom. We went to replace the electronic pump control box with a manual control box so that when the light is off and later comes on, since the on bottom is on and it is a manual one, the motor get its power and start operating without any body opening the power box. but when we got there, the manual control box was not able to switch on the motor, so it was getting late and we had to leave the old one there as it was.


On Wednesday, the 16th of December, 2015, we completed the project and handed it over to the community where the chief was not able to attend but some of the sub chiefs and some of the elders of the community were also there. PP was very happy and the community was also happy about the project. here are some of the pictures we took:

WHERE ARE THE PICs ????????????

And the TITEL is missing too all over !!!

Dienstag, 15. Dezember 2015



Today 15th of December, 2015, Sulley and I visited the site to complete the work there by fixing the float switch and the pump control. Later PP came there to check if every thing was okay. We went there at 11:00am and left there very late at 7:30 pm because we wanted to complete there work for the next day's handing over. here are some of the pictures I took on that day:






Montag, 14. Dezember 2015



Today the 14th of December, 2015, I went to the site to make sure that the floor concrete is casted, but when I went there, the masons were not available. I called them and they said they will cast it in the evening, so they were able to do it. Also, I went to buy the poly tank(5000 LT) and we were able to take it to the top. I also went to pay the painter who painted the metal gate, the bore hole cover and the power box. I was also able to go for the results of the water test. Here  are some of the pictures I took today:






Samstag, 12. Dezember 2015



Today on the 12th of December, 2015, the infra tec engineers visited the two sites in Nkwantakese to ix the pump. We were able to do that successfully the same day. here is a video.

Freitag, 11. Dezember 2015



because capedrill delayed the fixing of the pump, we were not able to visit the site until today that we went there because they are coming tomorrow. today on the 11th of December, 2015, Sulley and I went to the site to dig the ground 0.5m to fix the power box and also went to secure generator down to test the pump when it is fixed and tools like the spanners to the away the hand pump before fixing the EL pump. We left campus around 9:30am and left the site around 3:15pm. Here are some pictures I took when I was digging and mixing the concrete.









Freitag, 4. Dezember 2015



On the 3rd of December, 2015, all the Infra-tec engineers(PP, Stephen, Panford, Sulley and I) visited the two Nkwanta kese project.(gh it150928 and gh it150929). We first went to gh it150929 to see what is going on there and from there we went to gh it150928 to see how work was going. When we got to my site, we saw that every thing was ohky but just one pipe in the fetching station needs to be positioned well. When we were about to leave, I gave the welder some part of his work charge then from there we(Infra-tec engineers) went to blue eyes to have lunch.


I visited the site with Sulley on the 2nd of December, 2015. When we got there, we tried to pass a flexible rod through the pipes we laid for the wiring and we encountered a problem which we solved the problem. The problem was that, the flexible rod was not able to go through the pipes smoothly so we had to change the corners angle pipes we used. The plumber came to continue with his work but the masons did not come. I gave the plumber part of his work charge so he can complete the work. We took some of the water for the water test from my site and later went to Sulley's site to take some of the water from his site for the water test. We went there at 9:00am and left there at 3:00pm.

Dienstag, 1. Dezember 2015



i visited the site yesterday 30th November, 2015. The mason and the plumber were doing their work. The plumber was laying the pipes and the masons were plastering and dressing the wall and the pillars. The cement we bought got finished so we had to buy some more cement before the work can be completed. i gave some money for the filling of sand to be done for levelness before the concrete can be casted on the ground. I went there at 10:30 am and left there at 3:00 pm. Here are some pictures i took: