Freitag, 27. November 2015



Today on the 27th of November, 2015, i visited the site to make sure the mason continues the work. When i went there, they had finished laying the blocks for the fetching station and will start to fill the place before casting the flow concrete. i gave them their money for work charge. i gave the welder money to buy 2inch round galvanize pipe to fix the metal power box. I left to the site at 11:30am and left there at 3:40pm. Here are some pictures i took today:






Donnerstag, 26. November 2015


Yesterday, 25th of November, 2015, I went to the site with Sulley, to lay pipes for the wires before the down flow concrete can be casted. the masons are going to cast concrete around the iron rods on the flow before they can cast the 1m around the pillars. I was able to give the plumber the money to buy the materials for the plumbing works. I gave the carpenter and the steel bender the rest of their work charge and gave some money for water. I did digging for the laying of pipes. from 8:00am to 4:00pm. Here are some pictures I took:








Dienstag, 24. November 2015



i visited the site today, 24th of November, 2015, and made sure the steel bender and the mason worked on the down flow of the tower. also made sure the welder worked on the ladder for the tower and also gave some money to buy materials for bore hole cover. i went there at 11:00am and returned at 3:00pm. Here are some of the pictures i took:






Montag, 23. November 2015



On Friday the 20th of November, 2015, I visited the site and made sure the top concrete flow was casted and also made sure the welder worked the power box. Here are some of the pictures I took on that day:









 
 
 
 
Please this is the link to the account.
 
 
 
 
 

Donnerstag, 19. November 2015



Yesterday, 18th of November, 2015 from 7:30 am to 1:30 pm, Mr. Sulley and I went to the Nkwantakese site to lay the pipes for the wiring before the concrete can be casted. When we got there, the steel bender had not finished with his work, so the mason was waiting for him so he can start with the casting. So we were not able to lay the pipes. I was not able to update my blog yesterday because my laptop screen got spoilt and I went to replace it and when I got home, there was light out. I am going to complete the account today so I can send you the link. I was able to pay the carpenter, the steel bender and the mason part of their work charge.

Montag, 16. November 2015



Today on the 16th of November, 2015, i went to Nkwantakese water station. The carpenter was able to do the frame work with the wood to enable the steel bender to bend the iron rod to be fitted into the frame work done by the carpenter. The mason was waiting for the steel bender to finish with his work so they can cast the concrete. the stones and the sand were ready for construction. I gave money to the welder to buy the metal pipes for the metal gate, the power box and ladder to the tank. Today, when I got there, the carpenter and the steel bender were demanding some of their work charge money but I told them i cant give them money today but an sure to get them some of the money before Thursday.   I went there at 11:00 am and left there at 4:30 pm.

Here are some of the pictures I took today.

Here are the blocks for the construction of the fetching station


In this picture is the steel bender bending the iron rods to be put in the wood frame work before casting of the concrete.



 Beside the steel bender is the sand the mason is going to use for the concrete casting.


 This is the river side stones that the mason is going to use for the concrete.




These are the iron rod going to be used by the steel bender



These are the cements  going to be used by the mason

Samstag, 14. November 2015




I went to Nkwantakese with Mr. Sulley on Friday 13th of November, 2015. Mr. PP sent me GH 4000.00 on Thursday to start the project.   I cashed out the money on Friday @ western union money transfer. When we got to Nkwantakese, I ordered for 20 bags of ghacem cement, sand and stones, and gave money to buy iron rods and woods to start with the tower flow. we got there at 12:00 pm and left there at 5:00 pm

Donnerstag, 12. November 2015

Thu 12. Nov 2015 David get Finance to Start

WR GHS 4000 send by pp ...to coordinate Watertest with Proj 150929 and pump installation